Scope, schedule, and cost are the three pillars of project control — tightly linked through the Work Breakdown Structure (WBS).
1. The Scope–Cost–Schedule Relationship
- Scope defines what work must be done.
- The schedule defines when it will be done.
- Cost defines how much it will take.
If one element changes, the others must be adjusted.
For example:
- Expanding scope (adding a new floor) → increases both cost and schedule.
- Accelerating schedule (faster delivery) → increases cost due to overtime or additional crews.
2. Work Breakdown Structure (WBS) Integration
The WBS links activities to budget line items.
Each work package includes:
- Defined scope of work
- Assigned resources (labor, material, equipment)
- Estimated cost and duration
3. Time-Phased Budgets
A time-phased budget (or cost-loaded schedule) distributes total cost along the project timeline.
This helps managers:
- Monitor actual vs. planned spending
- Identify early cost overruns
- Forecast monthly cash requirements
4. Earned Value Integration
Earned Value Management (EVM) links:
- Planned Value (PV) – Budgeted cost of scheduled work.
- Earned Value (EV) – Budgeted cost of completed work.
- Actual Cost (AC) – Real cost incurred.
By tracking these, the project manager can measure:
- Cost Performance Index (CPI) = EV / AC
- Schedule Performance Index (SPI) = EV / PV
“Cost control is not about spending less — it’s about knowing when and why you’re spending.”