The testing and commissioning phase ensures that every system and component functions according to design intent before handover.

1. Testing & Commissioning (T&C) Objectives

  • Verify the mechanical, electrical, and plumbing (MEP) systems performance.
  • Ensure safety, quality, and compliance with design specifications.
  • Achieve operational readiness for occupancy and use.

2. T&C Process

3. Final Inspection Checklist

  • Civil finishes and punch list completion.
  • Electrical, plumbing, and HVAC verification.
  • Life safety systems: fire alarms, sprinklers, access controls.
  • Site and landscape inspection.
  • Final walkthrough with owner and consultants.

Output:

  • Completion Certificate
  • Snag List & Rectification Report
  • Commissioning Report

“A project isn’t complete when it’s built — it’s complete when it performs.”